General Contracting Construction Management Pre-Construction Services Construction Administration Facilities Management and Maintenance
CJS Builders - 30 Broad Street, 6th Floor, New York, NY 10004
EARL JEANS – 160 Mercer Street
5,800sf flagship for this is division of Nautica Enterprises located in a Landmarked Building in the heart of SoHo
Design Build Project was completed in 8 weeks
Work consisted of the demolition and extensive structural rehab of the existing structure
Design Team implemented existing industrial overhead trolley system into the new design allowing the Owner to easily reconfigure the store layout by sliding the interior millwork partitions on the overhead rails
All light fixtures, store fixtures, millwork and flooring were custom designed to create the new brand
New Mechanical, Electrical, plumbing and life safety systems were installed including new A/C equipment rigged to the 7th floor rooftop